City of Oceanside-Pure Water Oceanside-water recycling

Pure Water Oceanside Project Reaches Milestones

Pure Water Oceanside construction remains on schedule for completion in 2022, with several significant milestones recently completed. The Oceanside project will purify recycled water to create a new, local source of high-quality drinking water that is safe, drought-proof and environmentally sound.

“Construction has impacted many residents and businesses,” said Cari Dale, City of Oceanside water utilities director. “Please know the City of Oceanside appreciates your patience. We thank people for understanding the need for this project and bearing with us during these months of construction impacts. This work is temporary, but the benefits will last for generations.”

Pure Water Oceanside Project foundation walls in place

Now under construction, Pure Water Oceanside will purify recycled water to create a new, local source of high-quality drinking water that is clean, safe, drought-proof and environmentally sound. Photo: Jeremy Kemp, City of Oceanside

Now under construction, the project will purify recycled water to create a new, local source of high-quality drinking water that is safe, drought-proof and environmentally sound. Photo: Jeremy Kemp/City of Oceanside

The foundational work on the facility located in the San Luis Rey Water Reclamation Facility is complete. Pipelines, electrical conduits, equipment pads/pedestals, and wet wells have been constructed. Prefabricated walls have been installed. Installing the roof and additional wall stabilizing are next on the schedule.

The water purification equipment including pumps, membrane filters, and reverse osmosis canisters are currently being manufactured. Delivery is anticipated between this summer and fall.

Coco Farms Drive and Fireside Park construction update

Work on the south side of Coco Palms Drive near the El Camino Real intersection begins this month. Parking in the area will be closed during this work period with "no parking" signs posted. Map: City of Oceanside

Work on the south side of Coco Palms Drive near the El Camino Real intersection begins this month. Parking in the area will be closed during this work period with “no parking” signs posted. Graphic: City of Oceanside

The two injection wells on Coco Palms Drive are complete. Sound walls will be removed. Construction on two planned monitoring wells is anticipated to begin within the next two months. Sound walls will be installed prior to extended hours construction into evenings and weekends to reduce the impact on the community.

Coco Palms Drive will continue to be closed for the next few months while pipeline construction is underway.

Work on the south side of Coco Palms Drive near the El Camino Real intersection begins this month. Parking in the area will be closed during this work period with “no parking” signs posted.

Monitoring well work in Fireside Park will take place primarily during the daytime, with possible evening and weekend work for critical activities. Sound walls will be installed to reduce noise. Drilling and development is estimated to take six weeks.

El Camino Real recycled water expansion pipeline work coming soon

An overhead look at pipeline installation along Douglas Drive in Oceanside for Pure Water Oceanside project. Photo: Jeremy Kemp, City of Oceanside

An overhead look at pipeline installation along Douglas Drive in Oceanside for Pure Water Oceanside. Photo: Jeremy Kemp/City of Oceanside

Pipeline installation work will begin soon to install recycled water pipelines under El Camino Real. Traffic delays are expected and alternative routes are suggested.

Cones will be set up in work zones to redirect traffic from closed lanes and flagger workers will help drivers safely navigate intersections. Regular working hours will be Monday through Friday, 7 a.m. to 5 p.m. with occasional work on Saturdays.

Work at the Mission Avenue and El Camino Real intersection will be at night to reduce commuter traffic impacts. Work hours will be from 8 p.m. to 4 a.m.

Oceanside Project benefits both residents and environment

Construction personnel guide reverse osmosis skids into place. Photo: Jeremy Kemp, City of Oceanside

Construction personnel guide reverse osmosis skids into place. Photo: Jeremy Kemp/City of Oceanside

Approximately 90% of Oceanside’s drinking water is imported. Pure Water Oceanside will create three to five million gallons of drinking water each day, enough water to provide 32% of the City of Oceanside’s water supply.

The water purification process uses reverse osmosis and advanced oxidation to create safe drinking water. The technology removes pharmaceuticals, chemicals, hormones, microplastics, and personal care products.

The project protects sensitive ecosystems by reducing the amount of water siphoned by imported water sources. It decreases the amount of recycled water discharged into the ocean, and uses half the energy needed to transport imported water, reducing greenhouse gas emissions.

Residents are kept up to date on construction impacts to streets and other infrastructure through several outreach efforts including an interactive construction map, detailed online schedule, regular newsletters, and virtual open house presentations live on the City of Oceanside’s YouTube channel, offering residents the opportunity to ask questions.

Water News Network Top Stories of 2020

The Water News Network top stories of 2020 reflect the San Diego region’s interest in water conservation, the environment and efforts to diversify water supply sources. But the year was dominated by the coronavirus pandemic, which impacted water infrastructure and operations.

Second Lawsuit Filed Over San Diego’s Pure Water Project

Earlier this year, the city of San Diego filed a lawsuit against San Diego Gas & Electric in a dispute over the utility’s underground infrastructure obstructing the construction of a $1.4 billion water recycling project.

Now, a second and separate lawsuit has been filed on behalf of a San Diego resident claiming an agreement between the city and SDG&E to help get the project started is illegal.

Pure Water Oceanside Installing New Pipelines and Drilling Wells

Pure Water Oceanside is installing new pipelines and drilling wells as the recycled water project continues on track for completion in 2022. The advanced water purification project, and expansion of the City of Oceanside’s existing recycled water system, will deliver a new, local source of high-quality drinking water supplying more than 30% of the city’s water supply when completed.

Night construction is underway for the Pure Water Oceanside project including well drilling. Photo: City of Oceeanside

Pure Water Oceanside Installing New Pipelines and Drilling Wells

Pure Water Oceanside is installing new pipelines and drilling wells as the recycled water project continues on track for completion in 2022. The advanced water purification project, and expansion of the City of Oceanside’s existing recycled water system, will deliver a new, local source of high-quality drinking water supplying more than 30% of the city’s water supply when completed.

Residents are kept up to date on the progress of construction for the Pure Water Oceanside project. Photo: City of Oceanside

An interactive construction map is one of several sources for information about the Pure Water Oceanside project. Photo: City of Oceanside

Residents are kept up to date on construction impacts to streets and other infrastructure through several outreach efforts including an interactive construction map, detailed online schedule, regular newsletters, and virtual open house presentations live on the City of Oceanside’s YouTube channel, offering residents the opportunity to ask questions.

“We understand living and commuting near a construction site is not easy,” said Cari Dale, water utilities director for the City of Oceanside. “Everyone involved with the project is thankful to those residents and business owners who live and work in the construction zone for their patience and cooperation. It is crucial to the successful on-time completion of this vital infrastructure project.”

Pipeline construction

Pure Water Oceanside pipeline installation is now taking place at North River Road and the Douglas Drive intersection, and moving towards Pala. In addition, pipeline installation on Pala Road is now underway. The road will remain open both ways but will require lane closures. Photo: City of Oceanside

Pipeline installation at North River Road and the Douglas Drive intersection is moving towards Pala Road. Photo: City of Oceanside

Pipeline installation is now taking place at North River Road and the Douglas Drive intersection, and moving towards Pala. Lane closures on Douglas Drive allow access to the businesses through the entrance on North River Road.

In addition, pipeline installation on Pala Road is now underway. The road will remain open both ways but will require lane closures.

Well construction, which includes injection and monitoring wells, requires closing a section of Coco Palms Drive (south of Cherrystone Street), which will reduce construction time and impacts to nearby residents. Well drilling will continue 24 hours a day, seven days a week for approximately three weeks until early 2021. During this time, 16-foot sound walls have been installed around the drilling site to direct sound waves up into the atmosphere and away from residents. Night construction lighting will also be mitigated by the sound walls.

After drilling is complete, additional work will be conducted for testing and to install well infrastructure. The post-drilling work will take place weekdays during business hours and occasional Saturdays.

River Bike Trail remains open

Access map for the popular River Bike Path while the Pure Water Oceanside project construction is underway. Map: City of Oceanside

Access map for the popular River Bike Path while the Pure Water Oceanside project construction is underway. Map: City of Oceanside

Access to the popular River Bike Trail path is still accessible on the west side of Douglas Drive. Riders are asked to cross safely at the marked crosswalk at Pala Road and Douglas Drive to access the trail and avoid construction equipment.

Construction on schedule 

Well drilling will allow repurified water to be stored in underground aquifers. Photo: City of Oceanside

Repurified water will be stored in underground aquifers. Photo: City of Oceanside

Construction for the entire project is expected to be complete in 2022. While most construction will take place during regular weekday business hours, some critical pipeline construction elements will require temporary extended work hours and occasional Saturdays to complete the project on time.

Residents can sign up for email updates about the project. In the event of any immediate concerns, residents can call 760-435-4570 and representatives will troubleshoot issues.

Pure Water Project May Receive $6 Million for Construction

The U.S. Secretary of the Interior is planning to recommend a $6 million grant award for the construction of the Pure Water Oceanside project. Interior Secretary David. L. Bernhardt is planning to recommend the project for the grant award, which will come from the Bureau of Reclamation’s WaterSMART: Title XVI WIIN Water Reclamation and Reuse Projects funding opportunity.

The Bureau of Reclamation provides grants to water districts and communities like Oceanside trying to reclaim and reuse wastewater and compromised ground and surface water in the West. Pure Water Oceanside will purify recycled water to create a local source of potable drinking water.

The Miramar Reservoir dam under construction in 1960. The reservoir marks its 60th anniversary i 2020. Photo: Jeff Pasek, City of San Diego

Miramar Reservoir Marks 60 Years of Service

For 60 years, Miramar Reservoir has been an integral part of the City of San Diego’s drinking water system and offers San Diegans a popular recreational area. Now, the reservoir is being called into service to play a vital part in San Diego’s future Pure Water system to sustain a reliable water supply.

The City of San Diego is commemorating the 60th anniversary of Miramar Reservoir, its role in the region’s history, and the part the reservoir will play in the future.

“We celebrate not only Miramar Reservoir’s past, but the critical role it will play when the Pure Water system is completed,” said Shauna Lorance, director of the San Diego Public Utilities Department. “Miramar Reservoir will continue to be a key part of our water system for many years to come.”

Role in San Diego’s history

An aerial view of the Miramar Reservoir under construction in 1960. Photo: Jeff Pasek, City of San Diego

An aerial view of the Miramar Reservoir under construction in 1960. Photo: Jeff Pasek/City of San Diego

Miramar Reservoir marks 60

Miramar was the last of the City’s nine reservoirs to be developed. It was completed in 1960 as part of the second San Diego Aqueduct. The location previously had been the site of a small reservoir serving the vast ranch of newspaper publisher Edward W. Scripps.

Water flowing south to the reservoir originates from both the Colorado River Aqueduct and the California Aqueduct. The earthen embankment dam has a maximum height of 165 feet measured from the downstream toe, and has a base of 1,180 feet.

Dignitaries attend the Miramar Reservoir dedication ceremony in 1960. Photo: Jeff Pasek, City of San Diego

Dignitaries attend the Miramar Reservoir dedication ceremony in 1960. Photo: Jeff Pasek/City of San Diego

It was constructed by contractors Einer Brothers Inc. of Escondido and McCammon Construction, for $1.42 million. Land acquisition and engineering costs were approximately $730,000. Funds for the project came from an $11 million water bond approved by San Diego voters in June 1958.

When full, the reservoir covers 274 surface acres, reaches a maximum water depth of 114 feet, and has four miles of shoreline. Miramar Reservoir has a water storage capacity of 6,682 acre-feet.

Miramar Water Treatment Plant, which was completed in 1962 at a cost of $3.5 million, and expanded and upgraded in 2010, treats and filters drinking water distributed to customers in the northern part of San Diego.

Since the mid-1960s, the reservoir has been a popular recreational destination. An estimated 100,000 people visit Miramar each year to enjoy jogging, walking, biking, fishing, boating, picnicking, among other activities.

Miramar Reservoir to become part of Pure Water San Diego

Today in 2020, the Miramar Reservoir is poised to play a key role in the Pure Water San Diego project. Photo: City of San Diego

The Miramar Reservoir is poised to play a key role in the Pure Water San Diego project. Photo: City of San Diego

When the Pure Water system comes online, Miramar Reservoir will switch from holding imported water to holding purified water received through a pipeline from the planned North City Pure Water Facility. After water has been purified at the North City Pure Water Facility, it will then be transferred via pipeline to Miramar Reservoir. The Miramar Water Treatment Plant will clean the water again, and the water will be distributed to homes and businesses throughout northern San Diego.

Miramar Reservoir will continue use into the foreseeable future as it helps provide one-third of San Diego’s water supply locally by the end of 2035.

Popular Lake Miramar Gets Key New Role Just as it Turns 60

Lake Miramar, a longtime recreational oasis celebrating its 60th anniversary this year, is about to become a key part of San Diego’s new $5 billion Pure Water system that will boost the city’s water independence by recycling treated sewage.

The last of San Diego’s nine city reservoirs to be built, Lake Miramar attracts an estimated 100,000 people a year for jogging, biking, fishing, boating, picnicking and other activities.

FPUD Board, Others Tour Conjunctive Use Project Progress

The Fallbrook Public Utility District held a Nov. 10 tour of the Santa Margarita Conjunctive Use Project.

All five FPUD board members participated in the tour. If a majority of board members are present, an activity must be noticed as a public meeting, and members of the public were also invited to join the tour.

Pure Water San Diego Launches Guided Virtual Tour

The City of San Diego’s Pure Water Demonstration Facility public tour is now available as a virtual tour. A new video provides an up-close look at the technology behind the water purification plant.  In-person tours are on hold due to the coronavirus pandemic and will resume once it is safe to do so. Since opening in June 2011, nearly 19,000 people have toured the one-million-gallon-per-day facility in person.