Posts

CWA Approves Shutdown Schedule for Pipeline 5 Work at Moosa Creek

In 2019, the San Diego County Water Authority repaired a leak to a pipeline in Moosa Canyon. That repair was followed by an assessment of the other two SDCWA pipelines in the area, and one of those was found to be at risk so the CWA will be making repairs to that pipeline.

A CWA board vote, Feb. 27, authorized CWA general manager Sandra Kerl to take the necessary contracting and other actions for the repairs on Pipeline 5 in Moosa Creek. The current schedule includes shutdowns March 30 through April 5 for the installation of isolation bulkheads and May 18 to May 24 for the removal of the bulkheads as well as carbon fiber lining work expected April 6 through May 15.

May 24 is the Sunday of Memorial Day weekend, and the actual shutdown schedule will likely be revised as the repair work progresses.

Summers Are Starting Earlier, Finishing Later and Winter is in Retreat

Australia’s summers have lengthened by as much as a month or more in the past half century, exposing people to greater fire and heat extremes and placing ecosystems and farm crops at risk.

Researchers from The Australia Institute analysed data from 70 of the Bureau of Meteorology’s weather stations across southern and sub-tropical Australia, where the bulk of the population lives. They found in the past five years, summers were 50 per cent longer than they were in the mid-20th century.

MWD Grants SDG&E Permanent Easement in Pala

The Metropolitan Water District of Southern California granted San Diego Gas and Electric an permanent easement on MWD property in Pala.

The MWD board vote Feb. 11 approves the granting of the easement including conditions. SDG&E will obtain a 12-foot wide easement along the northern edge of the MWD property in the 39000 block of Pala Temecula Road.

MWD’s Pipeline 6 currently conveys water from Lake Skinner to Anza Road at De Portola Road in Temecula. That 7-mile segment is considered the northern reach of Pipeline 6; the southern reach would extend from Anza Road at De Portola Road to the San Diego County Water Authority delivery point approximately 6 miles south of the Riverside County line.

Everything You Need to Know About California’s Historic Water Law

California began regulating surface water in rivers and streams in 1914, but it took the state another 100 years to look underground.

In 2014, for the first time in its history, California passed a law regulating the use of groundwater – the resource on which 85% of its population and much of its $50bn agriculture industry rely.

SWA joins the California Statewide Communities Development Authority

The Sweetwater Authority (Authority) Governing Board voted to become a member of the Statewide Community Infrastructure Program (SCIP). The resolution passed at last night’s Governing Board meeting means that the Authority is now a member of the Statewide Communities Development Authority.

‘Baking Skills’ Used for Repair at Lake Hodges Pumped Storage Facility

You might not think ‘baking skills’ would come in handy to fix a recent problem at the Lake Hodges Hydroelectric and Pump Station Facility. But those skills, along with initiative and ingenuity, were demonstrated by San Diego County Water Authority staff as part of the creative and complex repair.

The facility connects the City of San Diego’s Hodges Reservoir with the Water Authority’s Olivenhain Reservoir. The connection provides the ability to store up to 20,000 acre-feet of water at Hodges for emergency use.

Hodges200 Team-Baking Skills-WNN

‘Baking Skills’ Used for Repair at Lake Hodges Pumped Storage Facility

You might not think ‘baking skills’ would come in handy to fix a recent problem at the Lake Hodges Hydroelectric and Pump Station Facility. But those skills, along with initiative and ingenuity, were demonstrated by San Diego County Water Authority staff as part of the creative and complex repair.

The facility connects the City of San Diego’s Hodges Reservoir with the Water Authority’s Olivenhain Reservoir. The connection provides the ability to store up to 20,000 acre-feet of water at Hodges for emergency use.

The Lake Hodges Hydroelectric and Pump Station Facility moves water between Olivenhain and Hodges, and is able to generate up to 40 megawatts of energy on demand, helping to manage electrical demands throughout the County. It also generates revenue and helps offset energy costs.

Ground fault alarm alerts staff

A ground fault alarm on August 25, 2019 alerted staff to a potential problem with Unit 2, one of the facility’s two 20-MW pump-turbine units. A series of tests and inspections by staff with the Water Authority’s Rotating Equipment team discovered the insulation on the copper bus bars of the generator’s rotor were worn and damaged. The bus bars are part of a system that provides DC power to the 12 electromagnets which surround the outer surface of the pump turbine unit’s rotor.

The rotors are designed to spin at 600 revolutions per minute and it’s the rotor’s electromagnets acting upon the stators windings that generates power. The electromagnets are connected together by copper bus bars located on top of the rotor and the bus bars are secured to the rotor by clamping plates and rim studs. The bus bars are insulated to ensure the copper does not touch any other metal surface and cause an inadvertent ground fault.

“Although a single ground fault may not damage the pump-turbine unit, it may prevent it from starting, if two ground faults were to occur, significant damage to the pump-turbine unit would occur and would also be an extreme danger to anyone within the facility,” said Jim Fisher, Water Authority director of operations and maintenance.

Creative solutions and ingenuity save time, money

Among various factors, the primary cause of the insulation failure was determined to be improper wrapping and curing of the insulation during initial installation.

Water Authority staff developed solutions and also took on the repair tasks in September. By doing the work in-house, the Water Authority avoided a more extensive outage due to long lead times required by contractors and vendors to perform the same work, saving time and money.

“Staff did an excellent job maintaining the operation of Unit 1 while making the repairs to Unit 2,” said Fisher, “which allowed the Water Authority to avoid a total shutdown and loss of all revenue during this period.”

HodgesRepairWNN-Water Authority

Initiative and ingenuity by San Diego County Water Authority staff led to a creative repair solution at the Lake Hodges Hydroelectric and Pump Station Facility. Photo: San Diego County Water Authority

‘Baking skills’ come in handy to create new bus bars

New copper bus bars were fabricated, and each had to be precisely wrapped by 5 different types of insulating tape materials. This wrapping process alone took approximately 8 hours per bus bar. The bus bars were then baked for ten hours within newly designed and fabricated aluminum molds to ensure proper pressure was applied to the insulation layers during the baking and curing process.

Staff efficiently re-purposed and utilized an oven that had been retained from the San Vicente Dam Raise Project to perform the baking. The Rotating Equipment team’s efforts produced excellent quality results which would have been difficult even for a vendor to meet. The newly insulated bus bars were re-installed, and the unit has been operating safely and without issues.

The initiative, ingenuity, and highly technical skills and knowledge of our staff were once again on display throughout the repairs,” said Fisher. “Their dedication, talents and outstanding efforts continue to ensure the Facility’s efficient and safe operation.”

Unit #2 was tested and placed back into service on November 17, 2019.

Along with the bus bar insulation and curing process repair, staff also performed many other highly technical, innovative and precise processes to complete this repair work.

City Reports Significantly Fewer Water and Sewer Spills in Past Year

San Diego is experiencing considerably fewer breaks in water mains and sewer lines thanks to continuing replacement of deteriorating cast iron pipes, according to a year-end report released Wednesday.

A total of 38 water main breaks were reported in the city in 2019, a 38% reduction from the previous year. It was the lowest total in 15 years and far less than the peak of 131 breaks in 2010.

New Inspection Tool Aids Vallecitos Pipeline Assessments

A new pipeline inspection tool being used by contractors working for the Vallecitos Water District to determine pipeline integrity could become a standard tool saving time and money.

After nearly completing construction in 2008, developers walked away from the 500-acre High Point subdivision in the City of Escondido. Water facilities installed for the subdivision were left unused for ten years.

San Diego Plans to Use Drones, Monitors to Reduce Water Main Breaks, Sewer Spills

San Diego sharply reduced the number of water main breaks and sewer spills across the city last year, saving ratepayers money and helping many neighborhoods avoid significant disruptions.

City officials credited the decreases to ramped-up maintenance and replacement efforts on water mains, sewer lines and pipes, particularly those made of cast iron.

And to further reduce breaks and spills, San Diego officials say they will soon begin using drones and other monitoring devices to look for early warning signs of potential problems.