You are now in California and the U.S. Home Headline Media Coverage category.

Unusually Warm May Contributes to Expanding Drought in the West

The Western drought has continued to expand and intensify, according to U.S. Drought Monitor data released Thursday.

Wet late-spring weather resulted in a slight decrease in the area deemed to be in extreme drought in Northern California.

Severe drought receded a little in parts of northeastern Utah and southwestern Washington. Unseasonably heavy precipitation, including high-elevation snow, fell in northeastern Utah, the Drought Monitor reported

Water Utility Hero of the Week-Olivenhain MWD-COVID19

Water Utility Hero of the Week: Gary Briant, Olivenhain Municipal Water District

Editor’s Note: This feature highlights water utility employees in the San Diego region working during the coronavirus pandemic to ensure a safe, reliable and plentiful water supply. The water industry is among the sectors that are classified as essential. Gary Briant, Olivenhain Municipal Water District Purchasing/Warehouse Clerk, is the Water Utility Hero of the Week.

Water Utility Hero of the Week: Gary Briant

Job/Agency: Olivenhain Municipal Water District Purchasing/Warehouse Clerk

How did you become interested in working in the water industry?

I spent many years working in the private sector. I noticed that my friends and family that worked in the water industry showed a real sense of pride in what they did. I wanted to stop the “rat race” in the private sector and join a team in the water industry where I could grow, contribute my skills, and be a part of something important. Working at OMWD feels like I’m part of a family, and I am very happy in my new career.

How has your job changed during the pandemic?

One of my duties here is to procure materials and supplies for Olivenhain. We have only had a few challenges finding supplies during the COVID-19 pandemic. Our general manager had the insight to make sure we were prepared very early on, so I was able to secure many items before vendors ran out and/or items became backordered for months. When some supplies were not available, we thought “outside the box” to find solutions. For example, we used the recipe from World Health Organization to make our own hand sanitizer when it was sold out everywhere.

How are you keeping safe?

It’s really important to me that I keep myself safe so I don’t put another team member or family member in jeopardy of getting sick. I’ve been focusing on maintaining social distance, sanitizing, and staying healthy. Safety and education has been the main priority at OMWD since the pandemic began. I make sure all needed safety items are well stocked so everyone at OMWD stays well. We have also transitioned to accepting deliveries in a no-contact manner.

What are you most looking forward to after the crisis ends?

I look forward to seeing everything go back to as close to “normal” as possible. I understand we will have to modify many ways that we operate regarding socialization and maintaining a safe work environment. But I look forward to the challenge of helping my co-workers stay healthy so OMWD can continue being successful in its mission to deliver safe and reliable water service to the community.

The Water Utility Hero of the Week highlights essential work performed during the COVID-19 pandemic by employees of the San Diego County Water Authority’s 24 member agencies.

San Diego County Water Authority Member Agency Map

Escondido Discusses Rehabilitating Lake Wohlford Dam

The Escondido City Council met on June 3 to discuss options for rehabilitating Lake Wohlford Dam, instead of building a replacement dam, and to award contracts for the Lindley Reservoir Replacement Project.

The council heard a report on the possibility of rehabilitating the Lake Wohlford Dam, which was first constructed in 1895 as part of Escondido’s local water system, to address seismic deficiencies rather than replacing the dam altogether.

According to the report, replacing the dam would cost more than $46.4 million, an amount much greater than the 2012 preliminary cost estimate of $30 million. Furthermore, it would cost an estimated $3.5 million to offset known negative impacts to the environment.

Regional Conveyance Study-Colorado River Aqueduct-RCS-primary-June 2020

Draft Study Highlights Region’s Water Conveyance Options

A draft report released today by the San Diego County Water Authority shows that building a new conveyance system to transport regional water supplies from the Colorado River Quantification Settlement Agreement is cost-competitive with other long-term options for meeting the region’s water needs.

The draft Phase A report is under review by water officials across the region. The Water Authority’s Board of Directors is expected to decide whether to move to Phase B at its July 23 meeting.

“By releasing this draft report – along with an independent review of key financial assumptions – we are trying to spark a thoughtful dialogue about our region’s water future,” said Dan Denham, deputy general manager for the Water Authority. “Given the long lead time for major water infrastructure projects, it’s important that San Diego County wrestle with these complex questions today so we can control our own destiny tomorrow.”

The Phase A report is the result of technical and cost analysis by Black & Veatch Corp. and the economic analysis by Water Authority staff. The engineering firm conducted similar studies for the Water Authority dating back to 1996, assessing “single use” water-delivery projects in those studies. The current Phase A analysis looks at conveyance projects with multiple partnership possibilities and potential benefits for the environment, water agencies and others.

Two viable alternatives emerge

Three potential pipeline routes were studied in Phase A, and the draft report says two alternatives (3A and 5A) are cost-competitive with other options, such as relying more on Metropolitan Water District of Southern California or developing additional local supplies.

Phase A takes a conservative approach to cost protections, by not factoring in potential partnerships or other sources of funds. However, partnerships and other agreements could significantly reduce the cost and enhance the value of a regional conveyance system. Phase B would include more detailed analysis of potential partnerships and funding opportunities and more details about projected costs from MWD.

“A decision about the Regional Conveyance System cannot be made in the abstract,” said Kelly Rodgers, director of the Water Authority’s Colorado River Program. “It must be made based on a comparison of the available alternatives, and we look forward to additional analysis and perspectives from our member agencies in the weeks ahead.”

The Water Authority currently pays MWD to transport QSA water through the Colorado River Aqueduct to San Diego. The regional conveyance system would be designed to convey the QSA water, which in 2021 will reach its full amount of 280,000 acre-feet of water annually. The current Water Transfer Agreement between the Imperial Irrigation District and the Water Authority continues to 2047. Both agencies can agree to extend the transfer another 30 years to 2077.

Conveyance routes would connect to All-American Canal

Each of the potential conveyance routes would connect to the tail end of the All-American Canal where it meets the Westside Main Canal in the southwest corner of Imperial Valley.

Two of the routes would follow a southern corridor between the Imperial Valley and San Diego, with one route over the mountains paralleling the U.S./Mexico border and the other tunneling through the mountains. Both routes would end at the San Vicente Reservoir in Lakeside.

The third and northernmost route would follow the Westside Main Canal toward the Salton Sea, then flow past Borrego Springs, and through the mountains. It would eventually connect to the Water Authority’s Twin Oaks Valley Water Treatment Plant in San Marcos.

Draft report findings

  • The region will continue to need QSA water through 2112.
  • All three RCS alternatives are viable from a technical and engineering perspective.
  • Alternatives 3A and 5A are economically competitive and provide long-term reliability and low-cost water to the region.
  • Alternative 5C is not economically competitive with Alternatives 3A and 5A and will not be recommended for further study.
  • Alternatives 3A and 5A could be integrated without major changes to current Water Authority operations.
  • Potential multi-agency, multi-use partnerships and other agreements could significantly reduce the cost and enhance the value of each RCS alternative and provide regional benefits to San Diego, California and the Southwest.

To read the report, go to https://www.sdcwa.org/colorado-river-supplies-management.

CWA Ratifies Contracts, Accepts Notice of Completion for Pipeline 5 Repairs

Eventually the San Diego County Water Authority will develop and implement a long-term fix for the vulnerability of the three SDCWA pipelines in Moosa Canyon, but the short-term fix for Pipeline 5 is now complete.

A unanimous CWA board vote, Thursday, May 28, ratified four contracts approved administratively by CWA General Manager Sandra Kerl and authorized Kerl to accept the work as complete.

“Earlier this month, in May, we shut down Pipeline 5 to remove the bulkheads and we resumed normal operations on May 8,” Neena Kuzmich, engineering manager of CWA, said.

LAFCO Approves Detachment Review Committee

San Diego’s County’s Local Agency Formation Commission approved a committee to review issues regarding the proposed detachment of the Fallbrook Public Utility District and the Rainbow Municipal Water District from the San Diego County Water Authority.

An 8-0 LAFCO board vote June 1 approved the composition of the committee, although LAFCO executive officer Keene Simonds will appoint the specific members and the list of tasks for the committee.

“We have agreement with the County Water Authority, Rainbow and Fallbrook,” said county supervisor Dianne Jacob, who is the chair of the LAFCO board.

“We have consensus on the tasks. I think we have a working agreement on the composition,” Simonds said.

CWA Sets June 25 Rate Hearing

The San Diego County Water Authority hearing to approve calendar year 2021 rates and charges will be June 25.

The May 28 motion to set the rate hearing date along with the proposed rates and charges passed with 78.139% of the SDCWA weighted vote. Twenty-one CWA board members supported the motion. Fallbrook Public Utility District general manager Jack Bebee, who is also FPUD’s representative on the CWA board, cast one of the eight votes against the action. Tom Kennedy, who is the Rainbow Municipal Water District general manager and Rainbow’s CWA representative, abstained as did Lois Fong-Sakai, who is one of the city of San Diego’s representatives on the CWA board.

A non-voting presentation earlier in the day addressed proposed changes to the CWA’s two-year budget which covers fiscal year 2019-2020 and fiscal year 2020-2021; the June 25 CWA board meeting will also include consideration of the budget adjustments. If the rates and charges are approved June 25, the action will also allocate the pro-rata shares of total fixed charges to each CWA member agency.

Opinion: Beyond COVID and Social Unrest, Valley’s Big Problem Remains Declining Groundwater

In these extraordinary times, managing groundwater for long-term sustainability may not seem like a top priority. But in the San Joaquin Valley — where groundwater supplies have been declining for decades — excess pumping is a critical problem, with major implications for public health, jobs, the environment and local economies.

The state’s Sustainable Groundwater Management Act (SGMA) requires groundwater planning and actions to sustain this vital resource. Agencies from California’s 21 “critically overdrafted” basins — including 11 large basins that span most of the San Joaquin Valley floor — submitted their first groundwater plans in January.

Vallecitos Water District Employs Technology to Decrease TSS, pH and Algal Blooms

Vallecitos Water District provides 5.25 million gallons of recycled water for irrigation every day. To fulfill the demands of modern irrigation systems, it is important to maintain low TSS levels. This is a challenge during the warm months in California, as algae that occur with raising temperatures, increase the level of TSS and clog the filters that are meant to remove TSS before the distribution of water to the irrigation systems.

Vallecitos Water District is known for its’ sustainable and innovative focus when it comes to water and wastewater treatment.

FPUD Board Tours Conjunctive Use Project Sites

The five Fallbrook Public Utility District board members were given a tour of FPUD’s Santa Margarita Conjunctive Use Project sites May 29.

Because a majority of the FPUD board members were present, it was legally required to be a noticed public hearing and the tour was officially a special meeting of the FPUD board. Although members of the public were welcome to attend they would have been required to remain in their own cars or trucks due to the coronavirus quarantine, but they would have been able to hear the audio communications.