Three Winter Aqueduct Shutdowns Lie Ahead

Valley Center Municipal Water District and its customers are long accustomed to dealing with periodic aqueduct shutdowns which allow the district’s sole wholesale water supplier, the San Diego County Water Authority, to inspect, repair, and make improvements to our imported water aqueduct system. 

However, this coming winter will be especially challenging, as there will be three consecutive aqueduct shutdowns in fairly rapid succession: (1) December 4 –14, 2022, (2) January 22 – February 1, 2023, and (3) February 26 – March 8, 2023.

At play is the fact that the three tunnels on the 1st San Diego Aqueduct (“1st Aqueduct”) need to be relined to protect the quality of the treated water traveling north to south through the enclosed aqueduct, and restore its operational integrity. The 1st Aqueduct serves five of VCMWD’s seven Aqueduct Connections, spanning the full length of the District’s 100-square-mile service area. Although VCMWD does have a connection to the 2nd San Diego Aqueduct (“2nd Aqueduct”), the 1st Aqueduct provides water to approximately 85% of the District’s service area. Completed in the early 1950s, the 1st Aqueduct began serving the fledgling Valley Center Municipal Water District soon after its formation election in 1954 and has served the district continuously for 67 years.    

LAFCO Approves Municipal Service Review, Sphere Updates for RCDs

San Diego County’s Local Agency Formation Commission approved municipal service reviews for the county’s three resource conservation districts while also updating the sphere of influence for each RCD.

Separate 8-0 LAFCO board votes Monday, Feb. 1, approved the municipal service reviews for the Resource Conservation District of Greater San Diego, the Mission Resource Conservation District and the Upper San Luis Rey Resource Conservation District while approving a sphere of influence update for each RCD which does not alter the sphere boundaries. LAFCO also had a presentation and discussion on the Sustainable Groundwater Management Act that morning, although no board action was taken.

LAFCO Report Recommends County Taking Over VC Parks

As expected, San Diego County LAFCO’s Municipal Service Review of the Valley Center Municipal Water District, Valley Center Fire Protection District and VC Parks & Rec District (which is referred to in the report as  VC Community Services District)—now available for public review—includes a recommendation that the County take over the parks district, and that the parks be put under a standalone County Service Area that would be run by the County, although with an advisory committee that would probably start with the current board of directors. 

Crews install a carbon fiber liner in Pipeline 4 in October 2019 to give the pipeline several more years of service while a longer-term solution is developed and deployed.

Pipeline 4 Repairs Completed In North San Diego County

Pipeline 4 – one of the San Diego region’s major water pipelines – is back in regular service after a leak was repaired, a testament to the San Diego County Water Authority’s proactive asset management program.

The pipeline resumed normal operations November 10 after nearly two months of modified operation. The leaky section was near Camino Del Rey in Bonsall, in an area with no adjacent homes or businesses.

“The shutdown and repair work went smoothly, and we could not have done it without the support and coordination from Water Authority staff, our contractors and member agencies, particularly, Fallbrook PUD, Rainbow MWD, Valley Center MWD, and Vallecitos Water District,” said Neena Kuzmich, Water Authority engineering manager.

Carbon fiber section will protect Pipeline 4

Water Authority crews detected a leak in the 90-inch diameter Pipeline 4 in the Moosa Canyon area in August.

Crews installed bulkheads in the pipeline to isolate the leak area for repairs. The bulkheads allowed the pipeline to continue treated water deliveries throughout the county in a modified fashion and restored full service to retail water agencies.

The Water Authority installed a carbon fiber liner to give the pipeline several more years of service, while a longer-term solution is developed and implemented.

Once the repairs were completed, a second shutdown was needed to remove the bulkheads and return the pipeline to full, normal operations.

Pipeline 4 is one of five major pipelines operated by the Water Authority.

Crews installed a carbon fiber liner to repair a leak in Pipeline 4 in north San Diego County.

Crews installed a carbon fiber liner to repair a leak in Pipeline 4. The liner will give the pipeline several more years of service while a longer-term solution is developed. Photo: Water Authority

Proactive approach keeps pipelines healthy

By relining the pipes and conducting timely repairs with the latest technology, the Water Authority has avoided major pipeline failures for more than decade.

Extending the life and reliability of major pipelines is one facet of the agency’s proactive asset management program. Real-time monitoring and other pipeline assessment tools help the Water Authority avoid pipeline failures by identifying potential problems in advance.

As part of its proactive approach, the Water Authority continually assesses and rehabilitates pipelines serving the San Diego region. The agency operates 310 miles of large-diameter pipelines, along with 1,600 aqueduct-related structures, and approximately 100 metering/flow-control facilities.

Approximately 82 miles of the pipelines are pre-stressed concrete cylinder pipes. These types of pipes were installed between the early 1960s and late 1980s and have experienced premature failures and shown areas of degradation.

In the past few years, the Water Authority has continued to extend the service life of pipelines with relining projects, including Pipeline 3 between Lake Murray and Sweetwater Reservoir, and Pipeline 5, in the Fallbrook area.

Water Authority staff inspect leak in Pipeline 4

Pipeline 4 Repairs Underway in North San Diego County

A recently discovered leak in a section of a pipeline in North County will be repaired in coming months while Pipeline 4 returns to service.

Crews have installed bulkheads in the pipeline to isolate a portion of Pipeline 4 for repairs. This will allow the pipeline to continue treated water deliveries throughout the county in a modified fashion starting the week of Sept. 16 and restores full service to retail water agencies. With the leaky section isolated, crews will make necessary repairs.

Four Water Authority member agencies – Fallbrook PUD, Rainbow MWD, Valley Center MWD, and Vallecitos Water District – have taken steps to manage water supplies while the pipeline was shut down to install the bulkheads.

Carbon fiber section will protect pipe

In August, Water Authority crews detected a leak in the 90-inch diameter Pipeline 4, one of five major pipelines the agency operates. The leaky section is near Camino Del Rey in Bonsall, in an area with no adjacent homes or business.

To find the cause of the leak, the Water Authority dewatered the pipe starting Sept. 9. Preliminary results of the investigation are that a weld seam, connecting a steel pipe section to a pre-stressed concrete cylinder pipe, separated in an area of very high water pressure.

The Water Authority is preparing to install a carbon fiber liner to give the pipeline several more years of service while a longer-term solution is developed and deployed.

After repairs are completed, a second 10-day shutdown of Pipeline 4 will be needed to remove the bulkheads and return the pipeline to full, normal operations.

Proactive approach keeps pipelines healthy

As part of its proactive approach to asset management, the Water Authority continually assesses and rehabilitates pipelines serving the San Diego region. The agency operates 310 miles of large-diameter pipelines, along with 1,600 aqueduct-related structures, and approximately 100 metering/flow-control facilities.

Approximately 82 miles of the pipelines are pre-stressed concrete cylinder pipes. These types of pipes were installed between the early 1960s and late 1980s, and have experienced premature failures and shown areas of degradation.

By relining the pipes or conducting timely repairs with the latest technology, the Water Authority has avoided major pipeline failures for more than decade.

 

County Water Authority Treatment Plant Malfunction Leads to Massive Notification of Water Customers

300,000 residents in San Diego County, including those in the Valley Center MWD service area, have or will receive written notices this week about a malfunction at the San Diego County Water Authority (SDCWA) Twin Oaks Valley Water Treatment Plant which occurred on April 21 and 22, 2019. While water quality was never actually impaired, federal regulations and state water officials have required that the notifications be sent.