CWA Approves Shutdown Schedule for Pipeline 5 Work at Moosa Creek
In 2019, the San Diego County Water Authority repaired a leak to a pipeline in Moosa Canyon. That repair was followed by an assessment of the other two SDCWA pipelines in the area, and one of those was found to be at risk so the CWA will be making repairs to that pipeline.
A CWA board vote, Feb. 27, authorized CWA general manager Sandra Kerl to take the necessary contracting and other actions for the repairs on Pipeline 5 in Moosa Creek. The current schedule includes shutdowns March 30 through April 5 for the installation of isolation bulkheads and May 18 to May 24 for the removal of the bulkheads as well as carbon fiber lining work expected April 6 through May 15.
May 24 is the Sunday of Memorial Day weekend, and the actual shutdown schedule will likely be revised as the repair work progresses.