As soon as 2026, the East County Advanced Water Program will deliver water to the faucets of customers. Photo: East County AWP milestone

East County Advanced Water Program Hits Multiple Milestones  

Work on the East County Advanced Water Purification Program facilities and pipelines reached multiple milestones at the start of 2024, and construction continues on schedule at multiple East County locations through 2025. As soon as 2026, the AWP will deliver water to the faucets of customers in the Padre Dam Municipal Water District, Helix Water District, Lakeside Water District service areas, and the northern portion of the Otay Water District service area.

At the main construction site north of Santee Lakes, more than 60% of the concrete has been poured for the water recycling, solids handling, and advanced water purification facilities. Nearly 60% of the 2.3 total miles of open-cut construction on wastewater pipelines that make up the AWP Program are complete.

More than 60% of the concrete has been poured for the East County Advanced Water Program water recycling, solids handling and advanced water purification facilities. Photo: East County AWP

More than 60% of the concrete has been poured for the East County Advanced Water Program water recycling, solids handling and advanced water purification facilities. Photo: East County AWP

Construction also continues on Fanita Parkway, north of Ganley Road in Santee, and within Santee Lakes Recreational Preserve. Pipeline water testing is now underway on that installed pipeline.

Work on the pipelines for the East County Advanced Water Program is affecting access to the Santee Lakes Recreational Preserve, which remains open. Photo: East County AWP

Work on the pipelines for the East County Advanced Water Program is affecting access to the Santee Lakes Recreational Preserve, which remains open. Photo: East County AWP

In addition, pipeline work at Santee Lakes is occurring between Lakes 3 and 4. There is a road closure and no parking in some areas. The Kiwanis Playground at Lake 4 remains open and parking has been preserved for playground visitors.

“Roughly a year and a half ago, we started with a blank slate and since then, the Joint Powers Authority and its project partners have made significant achievements at each of the construction sites,” said Mark Niemiec, director of the East County AWP. “It’s during these ongoing activities within the community including at Santee Lakes that we really appreciate our neighbors’ patience and understanding.”

Pipeline undergrounding scheduled this spring

These new pipelines servicing the East County Advanced Water Program will soon be moved underground. Photo: East County AWP

These new pipelines servicing the East County Advanced Water Program will soon be moved underground. Photo: East County AWP

The wastewater pipelines that will run from the East Mission Gorge Pump Station near State Route 52 to the first lake at Santee Lakes will soon be pulled underground. This trenchless construction method called “Horizontal Directional Drilling” minimizes the impacts to nearby waterways, including the San Diego River. The process takes an estimated 24 to 36 straight hours.

Elsewhere, Fanita Parkway will be temporarily closed for up to one week in March between Ganley Road and Lake Canyon Road to allow for paving on both sides of the street. Residents will see detour signs prior to the closure. The road closure will occur during the day from 7 a.m. to 5 p.m.

Purified water pipeline construction is continuing west on Mast Boulevard in Santee, as well as west on Mapleview Street in Lakeside and from Laurel Canyon Road to El Monte Road. Lane closures can be expected.

Residents and commuters in Santee and Lakeside can monitor road closures on the East County AWP website. Photo: East County AWP

Residents and commuters in Santee and Lakeside can monitor road closures on the East County AWP website. Photo: East County AWP

Construction on the 23,000-square-foot Visitors Center is in progress and will be completed by the end of 2025. It will house administrative offices, the operation control center, a testing laboratory, and a community room. The steel beam installation, including 66 columns and 100 beams, will use 350,000 pounds of U.S. steel.

The Flume Trail at Lake Jennings is officially back open following a 10-month closure for purified pipeline construction. The trail will close again during the summer for a couple of months to allow for additional pipeline construction near the shoreline.

The Flume Trail at Lake Jennings is officially back open following a 10-month closure. It will close again for additional construction later this summer. Photo: East County AWP

The Flume Trail at Lake Jennings is officially back open following a 10-month closure. It will close again for additional construction later this summer. Photo: East County AWP

When complete, the East County AWP Program will be able to create up to 11.5 million gallons of purified water per day, which is enough to serve an estimated 400,000 people, or roughly 30% of East San Diego County’s water supply.

The East County AWP Program includes construction of the following:

When operational, the East County AWP will be able to create up to 11.5 million gallons of purified water per day which is enough to serve roughly 30% of East San Diego County’s water supply. Photo: East County AWP

When operational, the East County AWP will be able to create up to 11.5 million gallons of purified water per day which is enough to serve roughly 30% of East San Diego County’s water supply. Photo: East County AWP

  • Water recycling facility treating 16 million gallons per day (MGD) of wastewater.
  • Advanced water purification facility treating and purifying 11.5 MGD.
  • Purified water pipeline transporting purified water 10 miles to Lake Jennings.
  • Wastewater and residual pipelines. Each segment is three miles long.
  • East Mission Gorge Pump Station (retrofitted) and City of San Diego partnership of regional brine and wastewater pipelines traveling from the pump station in Santee to the City of San Diego’s sewer line in Mission Valley.
  • Energy recovery system creating three megawatts of renewable energy.

To stay up-to-date with project schedules, community impacts and work descriptions, check the East County Advanced Water Purification Program’s interactive map on  www.eastcountyawp.com or visit @eastcountyawp on social media

San DIego Mayor Todd Gloria led a coalition of regional leaders urging a no vote on detachment by LAFCO at its Monday, July 10 meeting. Photo: San DIego County Water Authority protect ratepayers

Regional Leaders Seek to Protect Ratepayers from $200M Water Bill

San Diego Mayor Todd Gloria joined with regional agriculture, business, water, and elected leaders on Friday to oppose a potential $200 million water bill increase for ratepayers across San Diego County.

“The proposed action will have significant, long-term economic impacts to most households in San Diego County. Nearly every family and business will see an increase in their water rates,” Mayor Gloria said. “The cost of living is a continuous struggle for many San Diegans and these proposed rate increases are unacceptable.”

Chair Nora Vargas of the San Diego County Board of Supervisors commented on the proposal’s impact on low-income residents and the lack of a countywide vote. “An unnecessary increase in water bills means taking money away each month from hardworking families who can least afford it,” she said. “Not only will this detachment proposal lead to higher water bills, we also won’t have a say in the matter.”

Jerry Sanders, President and CEO of the San Diego Regional Chamber of Commerce, said it’s counterproductive to saddle businesses with additional bills. “This proposal would shift millions in added costs onto local businesses, many of which operate on thin margins,” Sanders said. “Our businesses face so many threats to success. Let’s not add to these challenges with an unnecessary water rate hike.”

A new study indicates original LAFCO cost estimates of detachment are as much as 50% below the true price tag, as much as $200 million. Photo: San Diego County Water Authority protect ratepayers

A new study indicates original LAFCO cost estimates of detachment are as much as 50% below the true price tag, as much as $200 million. Photo: San Diego County Water Authority

Cost Analysis of Detachment Called Flawed

Two water agencies in Fallbrook and Rainbow seek to leave the San Diego County Water Authority without paying the full cost of investments made on their behalf over the past several decades. On July 10, the San Diego Local Agency Formation Commission’s (LAFCO) board is expected to vote on the “detachment” proposal, possibly with the inclusion of a limited “exit fee” for Fallbrook and Rainbow. However, LAFCO’s figures are based on years-old data and flawed projections that understate the annual costs of detachment by at least 50%.

Updated figures released this week show that disadvantaged communities, working families, farmers, and others across San Diego County will be forced to pay nearly $200 million more over the next decade for water service unless the agencies seeking to leave the Water Authority are required to fully cover their costs. LAFCO’s data don’t reflect the inflationary realities or the fact that the financial impacts of detachment will continue far beyond LAFCO’s five-year horizon.

“I am deeply concerned that LAFCO could make this momentous decision without ensuring the accuracy of the costs of detaching from the Water Authority or allowing residents countywide to vote on this scheme,” said Water Authority Board Chair Mel Katz.

LAFCO’s staff recommendation to approve the detachment plan does not include a substantive analysis of impacts to disadvantaged communities or to agriculture in the Water Authority service area. Nor does it include the environmental analysis required by law.

Agriculture Deeply Affected By Proposal

“We all care about the cost of water because it’s a major factor for most farms,” said Frank Hilliker,” Board Chair of the Lakeside Water District and a long-time egg farmer in East County. “If Fallbrook and Rainbow water agencies don’t pay their costs, it hurts farmers like me who will be forced to pay more. I urge LAFCO to make sure that they require full cost coverage by Fallbrook and Rainbow to protect our region’s agriculture industry.”

A coalition of government, community, business, labor, agriculture, and water leaders joined together today to collectively urge San Diego LAFCO to vote no on detachment at its meeting on Monday, July 10. These leaders include:

  • Mayor Todd Gloria, City of San Diego
  • Chair Nora Vargas, San Diego County Board of Supervisors
  • Councilmember Stephen Whitburn, City of San Diego
  • Vice Mayor Colin Parent, City of La Mesa
  • District Director Janet Chin, Office of Assemblymember Tasha Boerner, District 77
  • Chair Mel Katz, San Diego County Water Authority
  • Vice Chair Nick Serrano, San Diego County Water Authority
  • Board Chair Frank Hilliker, Lakeside Water District & East County Farmer
  • President & CEO Jerry Sanders, San Diego Regional Chamber of Commerce
  • Vice President Carol Kim, San Diego & Imperial Counties Labor Council
  • Vice Chair Gail Goldberg, Metropolitan Water District of Southern California
The Helix Water District is the San Diego region’s second largest water utility, after the City of San Diego. Its service area includes La Mesa, Lemon Grove, El Cajon, Spring Valley, and other unincorporated areas of the county, with a population of 277,000. Brian Olney

Helix Water District Names Brian Olney New General Manager

The Helix Water District Board of Directors appointed Brian Olney as the organization’s new general manager, effective September 1, 2022. Olney was previously the Assistant General Manager and before that, the water district’s Director of Water Quality and System Operations.  He has 28 years of experience in the water industry.

“Brian’s experience spans system operations, water treatment plant operations and maintenance, water distribution and construction,” said Helix Board President Kathleen Coates Hedberg. “He’s been a member of the executive team since 2016, and he is knowledgeable about local and regional water issues. Brian is a leader and will make a smooth transition into the general manager role.”

“I am honored to be the next general manager of Helix Water District,” said Olney. “We provide an essential service to hardworking people, who expect us to do our jobs correctly and efficiently and provide clean, safe water at a reasonable price. I agree with that, and we meet and exceed those expectations every day.”

Summer job leads to water industry career

Brian Olney has been named General Manager of Helix Water District, effective Sept. 1, 2022. Photo: Helix Water District

Brian Olney named General Manager of Helix Water District, effective Sept. 1, 2022. Photo: Helix Water District

Olney, a native San Diegan, grew up in East San Diego County, and now lives in Santee with his wife, Brenda. He earned an associate’s degree in water science technology and is a graduate of San Diego State University, where he earned a bachelor’s and a master’s degree in public administration.

A summer construction job introduced Olney to a career in the water industry.

“I quickly realized how rewarding it was and embraced the public service aspect. It is truly enjoyable to meet customers and explain what we do or help them through an issue,” said Olney.

Olney worked in field operations for Lakeside Water District and as a water system operator for Otay Water District before joining Helix in 2000 as a water treatment plant operator. Olney maintains Grade 5 certifications from the California State Water Resources Board in water treatment and water distribution, the highest level of certification with ongoing education requirements.

Olney will oversee second largest water utility in San Diego County

Serving 277,000 customers, the Helix Water District maintains 16,892 valves and 56,504 water meters. Photo: Helix Water District Brian Olney

Serving 277,000 customers, the Helix Water District maintains 16,892 valves and 56,504 water meters. Photo: Helix Water District

The Helix Water District is the San Diego region’s second largest water utility, after the City of San Diego. Its service area includes La Mesa, Lemon Grove, El Cajon, Spring Valley, and other unincorporated areas of the county, with a population of 277,000. The Helix regional treatment plant also supplies water to Otay Water District, Padre Dam Municipal Water District, and Lakeside Water District in addition to its own customers, a total population of 500,000. Olney will oversee 150 employees and manage the FY2022-23 budget of $108 million.

“We are fortunate at Helix,” said Olney. “The board of directors are actively involved in the community and serve the district and our customers very well. Our employees are qualified, compassionate, and dedicated. I will continue to reinforce our values, and our goals and objectives, and we will work through the challenges we face.”

(Editor’s note: The Helix Water District, Otay Water District, Lakeside Water District and Padre Dam Municipal Water District are four of the San Diego County Water Authority’s 24 member agencies that deliver water across the metropolitan San Diego region.)

County Water Authority Makes SAWR Permanent

The San Diego County Water Authority has a program called the Transitional Special Agricultural Water Rate, and the SDCWA will be transitioning the TSAWR into a permanent program.

A unanimous CWA board vote on Nov. 21 approved making the SAWR permanent. An annual review of the SAWR will be conducted in conjunction with other rates and charges and the cost of service process to determine SAWR rates is expected to be completed in spring 2020.