East County AWP Updates Construction Progress for 2025

Progress on the East County Advanced Water Purification Program (East County AWP) continues on schedule at multiple East County locations, with an increasing number of milestones being reached as the project nears completion in 2025.

The East County Advanced Water Purification Program is an important water project for East San Diego County. When complete, it will deliver a clean, reliable, and local water source.

See a time-lapse video of 12 months of construction from January through December 2024.

Over the last 12 months, many milestones have been accomplished, including:

  • Completion of the purified water pipelines in Santee
  • Fanita Parkway has been repaved, curbs and sidewalks restored, and construction equipment removed
  • Completed 95% of concrete pouring required for the site
  • Completed 78% of all water pipeline construction
  • Installed the Lake Jennings inlet to allow purified water to flow into the lake before it is treated at the R.M. Levy Water Treatment Plant
The East County AWP achieved significant milestones in 2024.

The East County AWP achieved significant milestones in 2024, with more ahead in 2025.

Construction is set to begin in spring 2025 on a newly approved phase of the project that will include work within Mission Trails Regional Park. This phase includes the rehabilitation of the existing East Mission Gorge Force Main, which will help add capacity for increased sewer flows during rainy weather to the City of San Diego for treatment.

It also includes the construction of new pipelines in the East County to manage residuals, which are the organic residues removed from wastewater during the treatment process, sending them from the East County AWP Project around the City of San Diego’s Pure Water Program facilities as a regional solution to residuals management.

Tour the latest East County AWP construction progress in this video update.

Purified Water Pipeline Construction and Road Closures

Work on pipelines is ongoing in Lakeside at the following areas:

  • Riverside Drive from Riverford Road to Rio Camino
  • Channel Road from the bridge to Rio Camino
  • Channel Road from the bridge to Mapleview Street

Expect reduced travel lanes at these locations. Crews have completed purified water pipeline installation along Mast Boulevard, which is being followed by final roadway paving.

Final paving entails grinding and overlaying the existing roadway to be replaced with new asphalt. Crews use a remote-controlled trench roller to compact the top layer of material when paving the roadway.

Jack and bore excavation work is underway near State Route 67 and Mapleview Street in Lakeside ahead of purified water pipeline installation. Photo: East County AWP

Jack and bore excavation work is underway near State Route 67 and Mapleview Street in Lakeside ahead of purified water pipeline installation. Photo: East County AWP

Restoration Efforts Underway in Santee and Lakeside

As part of restoration efforts, residents may see hydroseeding, the spraying of a mulch-type mixture with seeds, and a binding agent to prevent erosion and protect the seeds.

Newly hydroseeded areas along Fanita Parkway in Santee where pipeline construction is complete. Photo: East County AWP

Newly hydro-seeded areas along Fanita Parkway in Santee, where pipeline construction is complete. Photo: East County AWP

Hydroseeding work is nearly complete along Fanita Parkway in Santee, with final work to be completed this spring. In addition to newly installed plants, El Monte Road in Lakeside was also recently hydro-seeded.

Avoid walking, dog walking, biking, jogging, and driving in hydro-seeded areas. These activities prolong the revegetation efforts and the length of time these areas are closed to the public.

Protecting Bird Species During Construction

Compliance with the Migratory Bird Treaty Act and general protection of wildlife within the project vicinity allows birds like this Bald Eagle to safely nest in the construction area during breeding season. Photo: East County AWP

Compliance with the Migratory Bird Treaty Act and general wildlife protection within the project vicinity allows birds like this Bald Eagle to safely nest in the construction area during breeding season. Photo: East County AWP

The East County AWP project is committed to complying with the Migratory Bird Treaty Act and protecting wildlife within the project areas.

The Migratory Bird Treaty Act protects common, game, and special-status bird species across the United States. This protection includes nests, eggs, and young. With the spring bird breeding season now underway, larger birds such as hawks, owls, and crows build their nests early in the season. Smaller songbirds start nesting in early spring.

If additional vegetation clearing is required, biologists supervise clearance once the absence of nesting is confirmed.

Stay Updated On Program Progress With Interactive Map

When completed, water from this project will be provided to customers in Padre Dam Municipal Water District, Helix Water District, and Lakeside Water District service areas, and the northern portion of the Otay Water District.

With construction in multiple locations throughout East County, the Program’s interactive map continues to be a valuable tool for residents and businesses to track where work is happening. The map is updated regularly and accessible 24/7 through the EastCountyAWP.com website. Information is also available via social media at @eastcountyawp

Progress is on schedule for completion of the East County Advanced Water Purification Program in 2025. Photo: East County Advanced Water Purification Program

East County Advanced Water Project Fall Progress Report

Progress on the East County Advanced Water Purification Program (East County AWP) continues on schedule at multiple East County locations with significant milestones in recent months. Project construction is scheduled through 2025.

The main project site at the purification treatment facility is busy, with roughly 280 workers working on completion. Nearly 90% of the concrete is poured, and facility components are arriving from as far away as Japan and Canada.

The East County Advanced Water Purification Program is an important water project for East San Diego County. When complete, the Program will deliver a clean, reliable, and local water source.

See a video update on the progress of the East County Advanced Water Project here.

Roof Rising on the East County AWP Purification Treatment Facility

The building housing the advanced water purification treatment facility is taking shape as the roof is being added.

Raising the roof at the main treatment facility. Photo: East County Advanced Water Purification Program

Raising the roof at the main treatment facility. Photo: East County Advanced Water Purification Program

Construction on the 23,000-square-foot Visitor’s Center will be complete at the end of 2025. It will house administrative offices, the operation control center, a testing laboratory, and a community room. Steel beam installation, including 66 columns and 100 beams, will use 350,000 pounds of U.S. steel. The roof has also been installed.

There are four water purification steps, including membrane filtration, reverse osmosis, advanced oxidation using ultraviolet light, and free chlorine disinfection. The advanced water purification facility will treat up to 11.5 million gallons daily for 50,000 households.

Water from this project will be provided to customers in Padre Dam Municipal Water District, Helix Water District, and Lakeside Water District service areas, and the northern portion of the Otay Water District.

Overnight Construction Underway Into November

Work underway on Fanita Drive in Santee. Photo: East County Advanced Water Purification Program

Work is underway on Fanita Drive in Santee. Photo: East County Advanced Water Purification Program

More than 70% of the purified water and wastewater pipelines are installed throughout Santee and Lakeside. In addition, an 18-inch diameter wastewater pipeline was pulled under the San Diego River and a nearby golf course. At 3,500 feet long, it is one of the longest horizontal directional drill operations ever in San Diego County.

Overnight work began in late October near and at the intersection of Mast Boulevard and Cuyamaca Street in Santee. Work hours are from 9 p.m. to 6 a.m. Monday through Friday. This night work will allow crews to install a purified water pipeline when the roads are less busy, minimizing impacts to the public.

For residents who live in the immediate area, information was mailed to affected households describing the work and providing contact information. Construction in this area is expected to last through the second week of November.

Interactive Map Helps Residents Stay Updated On Progress

With construction in multiple locations throughout East County, the Program’s interactive map continues to be a valuable tool for residents and businesses to track where work is happening. The map is updated regularly and accessible 24/7 through the EastCountyAWP.com website. Information is also available via social media at @eastcountyawp on Instagram and Facebook.

 

Helix Water District crews lower the five-ton replacement valve into place for installation. Photo: Helix Water District

Helix Water District Replaces Aging Key Water Valve

One of the largest water valves key to Helix Water District operations was recently replaced. The massive five-ton, five-foot diameter valve is one of the largest in the district’s operation.

This valve isolates a section of pipe allowing water from Lake Jennings to flow into the R.M. Levy Water Treatment Plant. This replacement addresses two needs: First, it replaces an aging valve, and second, it allows Helix Water District to make cost-effective improvements on a 62-year-old supply line feeding the water treatment plant.

Helix Water District crews prepare the five-ton replacement valve for installation. Photo: Helix Water District

Helix Water District crews prepare the five-ton replacement valve for installation. Photo: Helix Water District

Infrastructure Updates Preparing for East County Advanced Water Purification Program

The valve replacement is among the major improvements underway that will help move, treat, and deliver new water from the East County Advanced Water Purification Program. The program will come online for East County in 2026.

The East County AWP program creates a new, local, and drought-proof water supply using state-of-the-art technology. It will purify recycled water, producing up to 30% of East County’s drinking water.

All work on installing the replacement valve in its new location took place in one day. Photo: Helix Water District

All work on installing the replacement valve in its new location took place in one day. Photo: Helix Water District

The large valve isolates a section of the Lake Jennings pipeline, which moves water out of Lake Jennings and to the inlet of the Levy treatment plant. Since the new East County AWP water will flow through this pipeline 24 hours a day every day for the next 30 years, it is vital for the Helix Water District to inspect and make any necessary repairs to ensure the pipeline is in excellent condition before the new water source comes online. The old valve had exceeded its useful life.

Replacing the large valve also allowed the Helix WD to relocate the new valve, improving access for inspections and maintenance. The previous valve was located over 400 feet from where the water enters our treatment plant and upstream of our other supply pipeline, leaving this section of the pipeline filled with water.

The new water valve has an expected operation life of 50 years. Photo: Helix Water District

The new water valve has an expected operation life of 50 years. Photo: Helix Water District

Before relocating the new valve, Helix maintenance teams could only access this section of pipe during a treatment plant shutdown. While working on the old valve, the district needed to purchase more expensive imported water to serve its customers while the plant was shut down and unable to produce its regular supply.

With the new valve in place, fewer shutdowns will occur and prevent the need for purchasing supplemental imported water while performing maintenance and repairs. Relocating this valve and keeping the plant running was the best option for long-term operations and cost savings.

Water Valve Installation Complete In One Day

Maintenance professionals secure the new valve into place. Photo: Helix Water District

Maintenance professionals secure the new valve into place. Photo: Helix Water District

Construction started early in the morning by cutting out an existing pipe section near the treatment plant’s headworks. The new valve was lowered into position, aligned, welded together, and up and running within 14 hours. The valve is so large it takes more than 400 rotations to close it. The new value is expected to have a useful life of 50 years.

Current work to accommodate the East County AWP project is still in progress. It involves creating new access ways, removing the old valve, constructing a new vault, and preparing the Lake Jennings pipeline for inspection.

Proactive projects like the valve replacement reduce risk, give staff flexibility and redundancy, and prepare the Helix Water District for more efficient operations. Photo: Helix Water District

Proactive projects like the valve replacement reduce risk, give staff flexibility and redundancy, and prepare the Helix Water District for more efficient operations. Photo: Helix Water District

Once completed, the district will have longer-lasting infrastructure that can meet the demands of our region and future water supplies. Proactive projects like the valve replacement reduce risk, give staff flexibility and redundancy, and prepare the Helix Water District for more efficient operations.

To learn more about East County AWP, please visit https://eastcountyawp.com/