Poseidon’s Desalination Plan for Huntington Beach Delayed Again

After years of bureaucratic hurdles and increasing regulatory requirements, Poseidon Water was dealt yet another delay Friday, Aug. 7, in its pursuit of a controversial desalination plant in Huntington Beach.  The Regional Water Quality Control Board concluded three days of hearings on the project’s next permit by telling Poseidon it must return with a more robust, more detailed mitigation plan to offset the environmental damage the project will cause.