Posts

Soquel Creek Breaks Ground on Water Purification Center

The Soquel Creek Water District in California held a groundbreaking ceremony last week, commemorating the start of construction on its Advanced Water Purification Center – the core of the district’s Pure Water Soquel Groundwater Replenishment and Seawater Contamination Prevention Project.

 

Construction of 8 Miles of Pure Water Soquel Pipeline to Start

Construction on 8 miles of water pipeline that will be serve as life-blood for the Pure Water Soquel Project, is set to begin on May 24 in Santa Cruz. Three distinct components of building are set to take place during the next several months. From late May until June 15 crews will work around California Street, from the Santa Cruz Wastewater Treatment Facility to Laurel Street. After that, and until around July 6, construction will take place on Laurel Street to Chestnut Street. The third scheduled construction phase will run from July 6 through Aug. 12 on Chestnut to the west end of the Laurel Street Bridge.