Posts

First Aqueduct Maintenance Shutdown Runs Feb. 27-March 8

The final shutdown for scheduled maintenance of the San Diego County Water Authority’s First Aqueduct is scheduled to begin February 27. The shutdown will run through March 8, allowing crews to reline portions of the historic aqueduct and perform regular maintenance work that ensures a safe and reliable water supply for the region. Portions of the First Aqueduct were shut down earlier this year for similar work, as part of a proactive approach to saving on future maintenance or replacement costs.

shutdown season-First Aqueduct-maintenance shutdown

First Aqueduct Maintenance Shutdown Runs Feb. 27-March 8

(Editor’s Update: Work started Monday, February 27, as scheduled)

The final shutdown for scheduled maintenance of the San Diego County Water Authority’s First Aqueduct is scheduled to begin February 27. The shutdown will run through March 8, allowing crews to reline portions of the historic aqueduct and perform regular maintenance work that ensures a safe and reliable water supply for the region. Portions of the First Aqueduct were shut down earlier this year for similar work, as part of a proactive approach to saving on future maintenance or replacement costs.

The Water Authority and its member agencies are coordinating to minimize impacts to residents and businesses, while servicing pipelines that are more than 65 years old.

Customers of these affected retail agencies during the final planned shutdown should check with their local water utility if they have questions about localized impacts: Fallbrook Public Utility District, Rainbow Municipal Water District, Rincon del Diablo Municipal Water District, Vallecitos Water District, Valley Center Municipal Water District, Vista Irrigation District, Helix Water District, Yuima Municipal Water District, and the cities of San Diego, Poway and Ramona.

“Taking care of this critical infrastructure during the shutdown season extends the life of the First Aqueduct and helps to avoid both water emergencies and the high costs of emergency work,” said Eva Plajzer, the Water Authority’s director of operations and maintenance. “Maintaining our water delivery system in coordination with our member agencies ensures the continued safe and reliable supply that serves the region’s 3.3 million residents and our $268 billion economy.”

Maintenance work on pipelines is scheduled during low-demand periods to minimize impacts on water service.

The historic First Aqueduct was constructed in the 1940s (Pipeline 1) and in the 1950s (Pipeline 2). On November 28, 1947, the first Colorado River water flowed south from Riverside County for 71 miles into the City of San Diego’s San Vicente Reservoir via the First Aqueduct.

The Water Authority’s Asset Management Program is a key element of providing safe and reliable water supplies to the region. The agency continually assesses and inspects its 310 miles of large-diameter pipelines, which provide treated and untreated water to 24 member agencies in San Diego County. The program is widely recognized for pioneering work, including a patented inspection device.

As assets age, the Water Authority proactively replaces and repairs them to minimize impacts to member agencies and the public. Investments in the latest inspection technologies – including electromagnetic scanning, robotic inspections and 3D tunnel inspections – help the Water Authority’s asset management team detect defects in pipelines and related facilities.

(Editor’s Note: The Fallbrook Public Utility District, Rainbow Municipal Water District, Rincon del Diablo Municipal Water District, Vallecitos Water District, Valley Center Municipal Water District, Vista Irrigation District, Yuima Municipal Water District, Helix Water District, Ramona Municipal Water District, and the cities of San Diego and Poway, are 11 of the San Diego County Water Authority’s 24 member agencies that deliver water across the metropolitan San Diego region.)

“Shutdown Season” for Regional Aqueducts in San Diego County

Sections of the regional aqueducts in San Diego County will be shut down over the next six months for maintenance projects to ensure a safe and reliable water supply for the region. The San Diego County Water Authority and its member agencies are coordinating on the annual “shutdown season” to minimize impacts to residents and businesses, who are not expected to face service disruptions.

Pipeline 5-Shutdown-Shutdown Season-Asset Management

“Shutdown Season” for Regional Aqueducts in San Diego County

Sections of the regional aqueducts in San Diego County will be shut down over the next six months for maintenance projects to ensure a safe and reliable water supply for the region. The San Diego County Water Authority and its member agencies are coordinating on the annual “shutdown season” to minimize impacts to residents and businesses, who are not expected to face service disruptions.

Starting October 16, a portion of Pipeline 5 will be out of service for 10 days to accommodate annual maintenance on the entire untreated water system and to prepare for rehabilitation of other sections of the pipeline. The Water Authority has worked for months to coordinate with the affected retail water agencies: Olivenhain Municipal Water District, San Dieguito Water District, Santa Fe Irrigation District, Helix Water District, Sweetwater Authority, and the cities of San Diego, Oceanside, Ramona, Poway and Escondido. Customers should check with their water utility if they have questions about localized impacts.

Proactive asset management – regional aqueducts and Pipeline 5

The Pipeline 5 work will rehabilitate about 5,000 feet of 96-inch diameter prestressed concrete cylinder pipe by inserting and securing a steel pipe liner. This portion of the pipeline is within the City of San Marcos, between North Twin Oaks Valley Road and the Water Authority’s Twin Oaks Water Treatment Plant. When completed, approximately 50 miles, or 61% of the Water Authority’s existing prestressed concrete cylinder pipe will be relined.

“Proactive asset management and coordination with our member agencies ensures that the region’s major water infrastructure reliably serves the region’s 3.3 million residents,” said Eva Plajzer, the Water Authority’s director of operations and maintenance. “We have worked with our member agencies for several months to minimize any impacts to residents and businesses.”

Safe and reliable water supplies

The Water Authority’s Asset Management Program is a key element of providing safe and reliable water supplies to the region. The agency continually assesses and inspects its 310 miles of large-diameter pipelines, which provide treated and untreated water to 24 member agencies in San Diego County. The program is widely recognized for pioneering work – including a patented inspection device – that promotes water affordability by avoiding costly unplanned disruptions in service. Maintenance work is scheduled during low-demand periods to minimize impacts on water service.

Constructed in 1982, Pipeline 5 is a vital component of the Water Authority’s regional water infrastructure system, delivering untreated supplies from Lake Skinner in southwest Riverside County to the Lower Otay Water Treatment Plant in southern San Diego County.

In addition to the October upgrades on Pipeline 5, a series of three shutdowns on the Water Authority’s First Aqueduct is scheduled from December through April, when portions of the aqueduct will be relined, along with other maintenance.

(Editor’s note: The Olivenhain Municipal Water District, San Dieguito Water District, Santa Fe Irrigation District, Helix Water District, Sweetwater Authority, and the cities of San Diego, Oceanside, Ramona, Poway and Escondido are 10 of the San Diego County Water Authority’s 24 member agencies that deliver water across the metropolitan San Diego region.)