CWA Pipeline Repairs Completed Under Budget

The San Diego County Water Authority repairs to Pipeline 5 were completed under budget. The SDCWA board approved a notice of completion July 25, which releases the remaining funds to the contractor. Although J.F. Shea Construction, Inc., bid the project at $25,304,375, the Walnut-based company was able to work with CWA staff to reduce the cost and the final cost of the work was $24,748,135.61. “The project was completed on time and within budget,” said CWA senior construction manager Gary Olvera. The CWA has an asset management program which uses both an acoustic fiberoptic monitoring system as well as internal inspections during aqueduct shutdowns to detect and monitor deterioration of CWA aqueduct facilities.