Contract Change Order Approved For Erosion Control Project

The San Diego County Water Authority approved a change order for their Moosa Canyon Erosion Control project. The CWA board approval Oct. 25, adds $351,000 to the contract amount and is the third change order associated with the dewatering system needed to address groundwater, which was encountered at a higher level than expected. The newest change order increases the total contract amount with Granite Construction from $1,445,889 to $1,806,889, while changing the contract end date from Oct. 31 to Dec. 31.