They’ve Demolished Most Of Oroville Dam’s Troubled Spillway. What’s Next?

The preliminaries are just about over. Permanent structural repairs are about to begin at Oroville Dam. Five months after an unprecedented emergency forced a mass evacuation, state officials said Wednesday they’re ready to start replacing the now-demolished lower portions of Oroville’s main flood-control spillway. Construction contractor Kiewit Corp. plans to install the first slabs of concrete Thursday in the lower 350 feet of the spillway chute. The so-called “leveling concrete” will create a smooth foundation for structural concrete that will be poured on top, said Jeff Petersen, Kiewit’s Oroville project director.