The $24 million Pipeline 5 Relining Project in Fallbrook is expected to conclude in summer 2019. Photo: San Diego County Water Authority

Pipeline 5 Upgrades Begin in Fallbrook

A $25.3 million Pipeline 5 relining project is under way in North County to improve the reliability of the San Diego region’s water delivery system. The project involves rehabilitating approximately 2.3 miles of one of the San Diego County Water Authority’s regional wholesale water pipelines in eight segments along a 9.5-mile stretch through the community of Fallbrook.

Construction work will be done in phases and completed in summer 2019. When finished, the Pipeline 5 Relining Project will help extend the service life of this vital piece of infrastructure for more than 75 years. Generally, relining construction rehabilitates segments of pipelines based on their age and the need for improvements.

Relining process advances in well-planned stages

Construction activities in Fallbrook began September 19 with the installation of protecting fencing, establishing an entrance to the construction area, and clearing the site of all vegetation and debris for safety. The relining itself will begin in November.

In broad terms, the relining process begins with dirt being excavated to create an access portal or work area. The construction crews will conduct most of the work underground, inside the pipe. They will access the pipe by excavating, establishing, and entering the pipeline through nine access sites, or portals. The portals will be 25-foot by 60-foot excavated pits, spaced approximately 525 to 2,500 feet apart. At each portal site, 40 feet of existing pipe is removed to permit access inside the pipe to install relining materials.

The work involves removing 20-foot sections of old concrete pipe at each portals. Then, new steel liners are inserted into the existing pipe using a specialized pipe cart. Liners are installed into the entire pipe section. Once installed, the joints of the liner pipe are welded together. Each new steel liner is coated with a cement mortar lining. Finally, portals are backfilled and — after pipeline disinfection — the pipe is ready to be put back into service.

Community kept informed about project’s progress

Much of the construction work associated with the project is in Water Authority rights-of-way. Some portals within the unincorporated San Diego County portion of the alignment will be in undeveloped areas.

As people living and working in the area begin to see the activity, project team members will be available to address questions or concerns. Contact information including 24-hour phone numbers, email contacts, and website links are posted on nine informational signs along the construction route. Construction workers on site will also have contact information to pass out on request.

For more information, residents can call the 24-hour project information line at (877) 682-9283, ext. 7009 or email . A representative from the project team will respond within one business day.

Pipeline upgrades ensure safe, reliable water supplies

The Water Authority’s large-diameter pipelines extend approximately 310 miles to convey water throughout western San Diego County. Approximately 82 miles of these pipelines were installed between the early 1960s and late 1980s with pre-stressed concrete cylinder pipes, or PCCP, made from a combination of steel and concrete. First used during World War II to help minimize the use of precious steel, this pipeline type is used extensively around the world.

Numerous failures of similar pipes nationwide prompted the Water Authority to take proactive measures to reinforce its PCCP type pipelines with steel liners in an strategic, multi-decade program starting in 1991.

In addition, in 2003 the Water Authority started using an innovative carbon fiber technology to conduct urgent pipeline repairs, helping ensure a safe and reliable water supply to the region.

When the Fallbrook project is finished, the Water Authority will have rehabilitated approximately 47 miles of PCCP — more than half of the total in the Water Authority system.

The $24 million Pipeline 5 Relining Project in Fallbrook is expected to conclude in summer 2019. Photo: San Diego County Water Authority

Pipeline Upgrades Coming to Fallbrook in Fall 2018

A major water pipeline that runs through rural North County is getting the water industry’s version of a makeover.

The San Diego County Water Authority plans to start relining one of its regional wholesale water pipelines in fall 2018, extending its service life by more than 75 years. Construction is expected to last about one year, and most of the $24 million project will take place underground with few impacts to nearby residents.

Relining projects rehabilitate segments of pipelines based on their age and the need for improvements. Proactive assessments help the Water Authority avoid pipeline failures by identifying potential risks before they cause problems.

The Pipeline 5 Relining Project involves upgrading approximately 2.3 miles of pipeline in eight segments along a 9.5-mile stretch of pipeline that runs through Fallbrook. The Water Authority’s project team hosted an open house for residents and answered their questions at the Fallbrook Library on May 1.

Additional community presentations are set for May 21 at the Bonsall Chamber of Commerce, May 22 at the Rainbow Municipal Water District’s Board of Directors meeting, and the Fallbrook Chamber of Commerce, and June 18 at the Fallbrook Planning Group.

Relining effort saves money

The Water Authority manages 310 miles of large-diameter pipeline to convey water throughout San Diego County. Approximately 82 miles of these pipelines were installed between the early 1960s and late 1980s. These pre-stressed concrete cylinder pipes (PCCP) are made from a combination of steel and concrete.

First used during World War II to help minimize the use of steel, this pipeline type is used extensively around the world. Numerous failures in similar pipes nationwide prompted the Water Authority to take proactive measures to reinforce its PCCP pipelines with steel liners starting in the early 1990s.

Proactive assessments help the Water Authority avoid pipeline failures by identifying potential risks before they cause problems. To date, the Asset Management Program has saved water ratepayers more than $200 million by prioritizing repairs, avoiding unnecessary work and maximizing the service life of the region’s large-diameter water conveyance system, which includes pipelines ranging in diameter from 20 inches to 9 feet.

Fallbrook work mostly underground

Water Authority construction crews will conduct most of the work underground, inside the pipe. They will access the pipe by excavating, establishing, and entering the pipeline through nine access sites, or portals. The portals are excavated pits 25-feet wide by 60-feet long and spaced roughly 525 to 2,500 feet apart. At each portal site, 40 feet of existing pipe is removed to permit access inside the pipe.

Work isn’t active at all portals at the same time; crews will shift from one portal to another. Much of the work associated with the project will be within public street rights-of-way.

When the project is finished, the Water Authority will have rehabilitated approximately 47 miles of the 82.5 miles of PCCP in its system.

More information about the Fallbrook project, including details about upcoming meetings is on the Water Authority’s project webpage.